This letter is a notification for a scheduled temporary road closure of the Broadway between Victoria Street and Caxton Street.

This temporary road closure of Broadway is scheduled to begin on Friday 03rd May 2019 and finish on Sunday 05th May 2019. On those days, the road will be closed for 24 hours. During this closure, traffic will be detoured through the neighbouring streets.

We intend to commence at 8am on Friday and the works are anticipated to be completed at 6pm of the Sunday 05th May 2019. We also wanted to let you know that the appropriate dispensation to carry out the TC3A crane erection has been approved by the City of Westminster Council. A copy of the document can be found attached to project’s noticeboards on Victoria Street, Broadway and Dacre Street.

Please note that all businesses and walkway along the Broadway will remain open during the road closure.

If you have questions about the temporary street closure or would like to hear an update on the progress of the weekend works, please contact the below:

  • Friday: Aidan Lucas – Project Manager – 07786964072
  • Saturday: Eduardo Duran – Construction Engineering Manager – 07702 839544
  • Sunday: Jon Ankiewicz – Senior Construction Manager – 07525254769
  • Fri-Sun: Kenny Smith – Site Appointed Person (Lifting Operations) – 07903 179 852

We are determined to build on the positive relationships and we will work hard to keep you informed, engaged and up-to-date with progress and construction activity. At Multiplex, we have a strong focus on connecting with the communities where we work and we will welcome the opportunity to engage with you and understand any concerns you may have.