This is a notification for a scheduled weekend works taking place at the Broadway Project.

The installation of the TC4A crane is scheduled to begin on Saturday 25th May 2019 and finish on Monday 27th May 2019.

We intend to commence at 8am on Saturday and the works are anticipated to be completed at 5pm of bank holiday Monday 27th May 2019. We also wanted to let you know that the appropriate dispensation to carry out the TC4A crane erection has been approved by the City of Westminster Council. A copy of the document can be found attached to project’s noticeboards on Victoria Street, Broadway and Dacre Street.

Please note there will not be any road closures. All works will be carried out within the boundaries of the project. The other three cranes operating on site will be lifting and installing the fourth crane.

If you would like to hear an update on the progress of the weekend works, please contact the below:

  • Saturday: Eduardo Duran – Construction Engineering Manager – 07702 839544
  • Sunday: Alex Carneiro – Technical Engineer – 07718 559 994
  • Sun-Mon: Taha Afaneh – Site Manager – 07552 622 236
  • Sat-Mon: Kenny Smith – Site Appointed Person (Lifting Operations) – 07903 179 852

We are determined to build on the positive relationships and we will work hard to keep you informed, engaged and up-to-date with progress and construction activity. At Multiplex, we have a strong focus on connecting with the communities where we work and we will welcome the opportunity to engage with you and understand any concerns you may have.

We want to apologise in advance for any inconvenience.